Insulators – Kangan Petrorefinery – (400 kV Substation)

Project data

ClientKangan Petrorefinery
EPC contractorDarian Company
SupplierNekuNiru Company
Installation startApril – 2017
Installation endAugust 2017
Delivery and commissioningJanuary and February 2018

Technical properties

  • 400 kV Composite station post insulators
  • 400 kV Composite string insulators

Equipment supplied

InsulatorsFCI, LAPP